Connection Charges for Solar and Other Technologies  

Jemena will apply a connection charge to cover the costs and time for our team to assess your application. From time to time, we may be required to augment our network to facilitate your Embedded Generation system. Our team will contact you if we do need to make any augmentation and advise of any associated costs. 

Embedded Generation Connection Charges

 

Total On-Site Embedded Generation Type/ Size

Connection Service

Connection Charges (excluding GST) *Note

Inverter Energy System
(Up to 10 kVA per phase or 30 kVA 3-phase)

Basic Connection Service

Basic Connection fee (meter reconfiguration)

Inverter Energy System
Solar PV (up to 10 kVA per phase or 30 kVA 3-phase)
plus Battery Energy Storage System (BESS)
(up to 10 kVA per phase or 30 kVA 3-phase)

Negotiated Connection Service


(see table below for detailed solar & battery installation)

Inverter Energy System 
(>30 kVA to 200 kVA)

Negotiated Connection Service


   $2280  

Inverter Energy System 
(>200 kVA to 500 kVA)

Negotiated Connection Service

$3,360

Non- Inverter Energy System
(up to 30 kVA)

Negotiated Connection Service

$3,360

Non- Inverter Energy System 
(>30 kVA to 200 kVA)

Negotiated Connection Service

$3,960

Non- Inverter Energy System 
(>200 kVA to 500 kVA)

Negotiated Connection Service

$4,560

Inverter Energy System OR Non-Inverter Energy System
(>500 kVA to 1,500 kVA)

Negotiated Connection Service

$7,740

Inverter Energy System OR Non-Inverter Energy System
(>1,500 kVA to 5,000 kVA)

Negotiated Connection Service

$13,980

* Note: for embedded networks, the EG application must be submitted for the parent NMI and must include total inverter capacity (all existing and new embedded generators for each child NMI within the embedded network, behind the parent NMI/ gate meter). Jemena only has visibility of the parent NMI and does not have visibility of child NMIs. This EG application is required to be submitted to Jemena for and on behalf of the Embedded Network Operator (ENO), and paid by the ENO, who owns the parent NMI and is responsible for all the EGs within their embedded network. The EG connection agreement is between Jemena and the ENO.

* Note: for all negotiated connection services, further connection charges will apply. All Solshare at Jemena goes through negotiated connection process.

 

Connection Charge for Sites with an Inverter Energy System (Inc. Batteries)

 

All applications and fee are based on the total inverter capacity on site including any existing or new inverters.

** Fee Update:  The current fee of $550 applies to applications submitted on or before 20 September 2026. A revised fee of $700 will apply to all applications submitted from 21 September 2026 onwards.

 

1 Phase Sites

Case

Total Solar Inverter Capacity

Total Battery Inverter Capacity

Total Inverter Capacity

Connection Service

Approx. Fees

Export Conditions

1

<=10 kVA

0 kVA

<=10 kVA

Basic Connection Service

$0

Maximum export 5 kVA

2

<= 5 kVA

<= 5 kVA

<=10 kVA

Basic Connection Service

$0

Maximum export 5 kVA

3

<=10 kVA

<=10 kVA

<=20 kVA

Negotiated Connection Service

~$700

Maximum export 5 kVA

4

<= 5 kVA

6-10 kVA

7-15 kVA

Negotiated Connection Service

~$700

Maximum export 5 kVA

5

>10 kVA

0 kVA

>10 kVA

Negotiated Connection Service

~$2280+

As per assessment

6

>10 kVA

>10 kVA

20-30 kVA

Negotiated Connection Service

~$2280+

As per assessment

 

3 Phase Sites

Case

Total Solar inverter Installation

Total Battery inverter Installation

Total Inverter Capacity

Connection Service

Approx. Fees

Export Conditions

7

<= 30 kVA

0 kVA

<= 30 kVA

Basic Connection Service

$0

Maximum export 15 kVA

8

< 30 kVA

< 30 kVA

<= 30 kVA

Basic Connection Service

$0

Maximum export 15 kVA

9

30 kVA

<= 10 kVA

30-40 kVA

Negotiated Connection Service

~$700

Maximum export 15 kVA

10

< 30 kVA

10-30 kVA

<= 40 kVA

Negotiated Connection Service

~$700

Maximum export 15 kVA

11

> 30 kVA

0 kVA

> 30 kVA

Negotiated Connection Service

~$2280+

As per assessment

12

> 30 kVA

> 10 kVA

> 40 kVA

Negotiated Connection Service

~$2280+

As per assessment