*Note: for embedded networks, the EG application must be submitted for the parent NMI and must include total inverter capacity (all existing and new embedded generators for each child NMI within the embedded network, behind the parent NMI/ gate meter). Jemena only has visibility of the parent NMI and does not have visibility of child NMIs. This EG application is required to be submitted to Jemena for and on behalf of the Embedded Network Operator (ENO), and paid by the ENO, who owns the parent NMI and is responsible for all the EGs within their embedded network. The EG connection agreement is between Jemena and the ENO.
Additionally the export limit requirement for existing/installed child NMI EGs <=30kVA 3 phase, to be backstop exempt
• If installed on or after 1st Jan 2025 -> 0kVA export limit
• If installed before 1st Jan 2025 -> 5kVA per phase (15kVA 3 phase) export limit
Please refer to jen-embedded-networks-emergency-backstop-scenarios.pdf below.