Skip to main
jemena logo

Trial Tariffs

At Jemena, we are excited by innovation and exploring new ways of doing things. In response to customer demand, and under section 6.18.1C of the National Electricity Rules, we will introduce two new trial tariffs from 1 July 2026. These tariffs are in trial only, and the tariffs, structure and any other component may change as we respond to the results of the trial. 


Network prices represent only a portion of your bill. Your final bill will depend on your unique energy profile and your retailer’s fees and charges. For more information, contact us at 1300 131 871 or your electricity retailer.

 

Kerbside EV charging trial tariff

For the 2026-31 regulatory period, we are introducing a kerbside EV charging trial tariff, A20E. This trial tariff is for small business customers and is:

  • only available to kerbside pole-mounted chargers
  • subject to a capacity of less than or equal to 44 kW (dual 22 kW chargers)

The tariff structure and network prices for A20E for 2026-27 are outlined below.

 

A20E network tariff applicable from 1 July 2026 to 30 June 2027

Fixed charge ($p.a.) Peak energy (c/kWh) Off-peak energy (c/kWh) Solar soak consumption (c/kWh) Export during solar soak period (c/kWh) Export during peak period (c/kWh)
0 18.208 4.551 1.000 3.000 -15.000

Notes:

  • Tariff prices will update on 1 July each year.
  • All times are local times.

 

High-voltage (HV) storage trial tariff

For the 2026-31 regulatory period, we are introducing a HV large business storage trial tariff, A40B, for storage customers up to 5 MVA. This trial tariff is aimed at large business operators with large-scale storage technologies connected to the network. The network prices for 2026-27 for A40B are outlined below.

 

A40B network tariff applicable from 1 July 2026 to 30 June 2027

Fixed charge ($ p.a.)

Peak energy (c/kWh)

Off-peak energy (c/kWh)

SDIC charge (c/kVA/day)

28,648.418

5.360

0.000

0.000

Notes:

  • Tariff prices will update on 1 July each year.
  • The peak period is 4 pm to 9 pm every day. The off-peak period is all other times. The SDIC charging period is 4 pm to 7 pm weekdays from December to March. All times are local times.
  • Applies to any storage-only or battery-only site connected to the HV network with a capacity of no less than 500 kVA and no more than 5 MVA. 
  • Assumes no other consumption at the NMI other than the storage technology.
  • Available at the customer’s request and subject to JEN’s discretion.